Posted at 1:37 a.m., Monday, April 14, 2008

Kauai lane closures announced

Advertiser Staff

Lane closures for roadwork this week on Kauai, weather permitting:

KUHIO HIGHWAY

Intermittent delays of no more than fifteen minutes may be expected in both directions through Friday from 8:30 a.m. to 3 p.m., daily, as heavy equipment is positioned during construction activities at the following locations:

  • In Anahola, between Hui Road (near Mile Point 15) and Koolau Road (near Mile Point 20) for pavement resurfacing. Completion of this project is anticipated in May 2008.

  • In Wainiha, near the Wainiha Bridges for bridge installation and pavement surfacing work. Completion of this project is anticipated in April 2008.

  • North of Kilauea Town between Kilauea Road and Kalihiwai Road for guardrail repairs and shoulder lane maintenance. Completion of this project is anticipated in May 2008.

  • In Kealia, near the Pili Mai Ke Kai subdivision between Anahola Road and Kukuihale Road for intersection improvements and shoulder maintenance. Completion of this project is anticipated in October 2008.

    KAUMUALII HIGHWAY

    Intermittent delays of no more than fifteen minutes may be expected in both directions through Friday, from 8:30 a.m. to 3:00 p.m., daily, during construction activities at the following locations:

  • In Lihue, near Rice Street for slope stabilization of the hillside adjacent to the highway. Completion of this project is anticipated in April 2008.

  • In Koloa, approximately one mile east of Maluhia Road, near Mile Post 5.7, for shoulder lane improvements. Completion of this project is anticipated in May 2008.

  • In Kalaheo, between Lauoho Road and Hokua Road near the Kalaheo Jelly Factory for drainage and shoulder lane improvements. Completion of this project is anticipated in June 2008.

  • In Kalaheo, near Hokua Road for improvements to acceleration, deceleration and shoulder lanes. Completion of this project is anticipated in June 2008.

    MAALO ROAD

    PAVEMENT RESURFACING (Night Work)

    Maalo Road will be closed in both directions through Friday morning, from 6 p.m. to 6 a.m., nightly, for pavement resurfacing.